Thursday, September 01, 2011

A666 Road Improvement works in Darwen, Lancashire

Improvement works to the A666 Blackburn Road will start on Monday, September 12 2011.

The work, to replace the worn out surfacing between Earcroft Way and Hawkshaw Avenue, will take around six weeks to complete.

Temporary traffic lights will be in force and there will be some disruption. Motorists are advised to avoid the area if possible.

In order to minimise disruption when laying the final surface it will be necessary to close the road between Hollins Grove Street and Earcroft Way on the following Sundays: September 25, October 2, October 9, October 16, October 23 (provisional.)

When the road is closed a diversion route will be in place using Hollins Grove Street, Lower Eccleshill Road, Paul Rink Way and Earcroft Way.